·         Total Concrete Volume 31,770 CY

·         Eleven Stories of Light Weight Concrete

·         Tallest Building in Rancho Bernardo, CA

·         4,375 CY Mat pour Placed and Finished in 14 Hours

·          Architectural toppings at 11th Floor Terraces & Bridge

Creating the new North American headquarters for Sony Electronics began with a major concrete pour that was performed by Sundt’s own crews. They placed more than 4,300 cubic yards of concrete to create a three-foot-thick slab that spans 39,000 square feet.  The work was performed on a Saturday – beginning at 2:00 a.m. – to assure adequate supplies, since it used concrete from four different batch plants and required more than 400 delivery trucks. 

Best of the Best Office Category, Outstanding Architectural Design-Engineering News Record