This was a fast track project with construction beginning before the design was complete. The team experienced material shortages and price escalations because of hurricanes, but the project was completed on time and on budget.

This design-build, three-building complex includes a two-story, 80,000-square-foot main building with administrative and operations spaces, conference and training rooms; a one-story, 13,000-square-foot support services building; and a one-story, 20,000-square-foot enforcement building.