Graphite Solar I

  • Location:

    Wellington, Utah

  • Client:

    rPlus Energies

  • Delivery Method:

    Engineer-Procure-Construct

  • Year Completed:

    Spring 2022

  • Specialties:

    Power, Solar

Features & Highlights

  • 104-megawatt direct current (MWdc) photovoltaic system on 600-acre site
  • NEXTracker single-axis tracking system and 25 Sungrow central inverters
  • 138 kilovolt (kV) substation and transmission line
Project Overview

Graphite Solar I, an engineer-procure construct (EPC) project, consists of a 104-megawatt direct current (MWdc) photovoltaic system. The project supplies energy to the utility PacifiCorp, which holds a long-term power purchase agreement on behalf of a multinational technology company as part of their net-zero emissions goals.

Covering 600 acres of land, plant infrastructure includes a NEXTracker single-axis tracking system and 25 Sungrow central inverters, along with a 138 kilovolt (kV) substation and transmission line.