Teamwork Keeps Flood Control Project Above Water

DJI_0014
The White Tanks project was once a massive area of dirt and mud.

Choosing a new project delivery method kept the Maricopa County Flood Control District from seeing its budget wash away during work on the White Tanks Flood Structure in Buckeye, Arizona.

In the past, the District constructed similar projects using Design-Bid-Build and sometimes faced change orders that nearly doubled initial bid values because of outside agency inspections during construction.

IMG_2162
It’s now a flood control project that is coming in on time and on budget.

On White Tanks, the District decided to try Construction Manager at Risk and selected Sundt. Our Transportation Group partnered with agencies including the Arizona Department of Water Resources and the National Resources Conservation Service to write specifications exactly as the District expected, lowering the chances of costly change orders.

“It worked well,” said Preconstruction Manager Jeffrey Hamilton. “The only change order relating to additional cost was because of a flood event, and the District had a contingency to cover that.”

The joint venture with Rummel Construction consists of widening and extending an existing flood structure and adding upgrades, including an architecturally enhanced auxiliary spillway, drop inlet structures and principal outlet structures. While the initial contract value was $25.3 million, the team is looking to bring the cost down by about $1 million.

We’re delivering client value in many other ways, too, including using drone technology to provide required survey information to verify completed work for our payment purposes.

“This would be a difficult and costly task with a survey crew,” Project Manager Ryan Vlach said. “We found a drone company that was able to fly the site and provide the necessary information at a fraction of the time and cost.”

Preconstruction ended in January 2016 and construction began the next month. Even with a small change order extending the contract until August, the team intends to finish work by June.