Sellwood Bridge Concrete Pour a DIY Project for Joint Venture Team

Pour 1 Tower Crane Photo (2)
Sellwood Bridge crosses the Willamette River in Portand, Oregon.

The first of 11 deck pours for the main span of the Sellwood Bridge was a self-performed success for Sundt on Oct. 20.

Pour 1 Tower Crane Photo (1) Cropped
Sundt’s joint venture team self-performed the concrete work on the first of 11 pours on the bridge span.

The placement took 8.5 hours and involved 470 cubic yards of 4,000 PSI high-performance concrete with fiber. Fifteen craft employees used a 61-meter concrete pump to do the job.

The work required extensive coordination among the concrete supplier, concrete pump subcontractor, the joint venture quality control, Multnomah County quality assurance and Oregon Department of Transportation inspection teams.

Self-performing concrete construction enables Sundt to further ensure quality craftsmanship and save clients money.

Sundt and joint venture partner Slayden Construction are constructing the new Sellwood Bridge over the Willamette River in Portland, Oregon using a unique “shoofly” approach.The structure replaces a 2,000-foot-long, aging bridge.

The project is scheduled to wrap next year.