• The project was built with a fast track design and a complicated schedule.
  • Sundt provided a state-of-the-art, high performance refrigeration system to meet the challenges of a 7,000-foot-deep shaft with rock temperatures reaching 170 degrees.
Installed the Number 10 Shaft cooling system, including the York refrigeration machine, in the existing compressor building.  Included in the project were: one condenser cooling tower set complete with the condenser cooling tower pump station; concrete structures; steel pipe supports; insulated 24-inch and 28-inch VIC pipe; tie into the existing AIR refrigeration system; and all required electrical, instrumentation and controls.