Messy Job has Clean Finish on US 175 Project

 |  Civil & Transportation
US 175 photo 1
Despite wet conditions, we completed our work on US 175 in Texas seven months ahead of schedule.

US 175 in Henderson County, Texas is bigger, safer and open well ahead of schedule despite conditions that often worked against our crew, which numbered as many as 50 craft professionals at a time.

The county, located 35 miles west of Tyler, Texas, saw 115 inches of rain in 2016. Seventy of those inches came during the spring, when our team was working on critical portions of the job, including constructing several large cast-in-place box culverts and four bridges and excavating 800,000 cubic yards of dirt.

“The soil is sandy and prone to washing out,” said Area Manager Abel Ortiz. “It was just a messy job site. Lots of water. The crew did a good job of managing all that.”

Construction of the drainage box culverts was a challenge under the conditions and the earthwork operations suffered significant delays. We had an answer that kept the Texas Department of Transportation project on track.

“The team made up for most of the lost time by double-shifting the dirt work operations during the summer,” Abel said. “We had five dirt crews going around the clock. At one point, crews were moving 20,000 cubic yards of dirt per day.”

The work turned US 175 into a four-lane divided highway that bypasses the small town of Poynor. The old roadway had two lanes with no shoulders in a rolling hill area, making it extremely dangerous.

Work started in October 2015 and was completed in January 2018, seven months ahead of schedule.

“The crew was able to manage the adverse weather very well,” Abel said. “That kept the owner happy.”